82. The authorization holder must design and build the stratigraphic survey so as to
(1)  comply with the Industry Recommended Practice, IRP: #25, Primary Cementing, published by the Drilling and Completions Committee;
(2)  ensure work safety;
(3)  prevent incidents in the maximum load conditions normally foreseeable during the life cycle of the stratigraphic survey;
(4)  withstand potential conditions, forces and stresses;
(5)  ensure a resistance sufficient for fluid kicks;
(6)  protect the integrity of the groundwater;
(7)  allow the characterization of the geological formations targeted; and
(8)  allow activities for controlling the pressure of the bottom of the stratigraphic survey in a constant and safe manner.
O.C. 1252-2018, s. 82.
In force: 2018-09-20
82. The authorization holder must design and build the stratigraphic survey so as to
(1)  comply with the Industry Recommended Practice, IRP: #25, Primary Cementing, published by the Drilling and Completions Committee;
(2)  ensure work safety;
(3)  prevent incidents in the maximum load conditions normally foreseeable during the life cycle of the stratigraphic survey;
(4)  withstand potential conditions, forces and stresses;
(5)  ensure a resistance sufficient for fluid kicks;
(6)  protect the integrity of the groundwater;
(7)  allow the characterization of the geological formations targeted; and
(8)  allow activities for controlling the pressure of the bottom of the stratigraphic survey in a constant and safe manner.
O.C. 1252-2018, s. 82.